Construction Project
After several months of planning and design,
excavation for the new ACES library
on the University of Illinois campus
began in May 1999. The project is sponsored
and will be owned by the Board of
Trustees for the University of Illinois. Six
separate contractors are working
together under one general contractor. The
project, which began in May of
1999, is scheduled to be completed by February
2001. Through informal
interviews with Charles O. Pickar we learned that the
project is 4-5 weeks
behind schedule. Pending weather conditions 25 to 35
workers usually present
on site. The typical workday can run between 6:30am and
depending on
deadlines can last until 9-10pm. As of the third week in January
2000,
the concrete foundation and the steel framework for the five-story
structure,
with the exception of the roof, were intact. The appendix of this
report
contains photographs of observed procedures and site materials.
Observed
Operations January 27, 2000 On the morning of January 27, two
massive 18-wheel
trucks carrying various shapes and sizes of steel beams were
unloaded on site.
It took almost two hours to unload each truck. A crane
approximately 200 ft.
high was used to move the steel from the truck onto
wooden planks on the ground.
The steel was separated by shape, and by
using the quite large reaching span of
the crane, the workers were able to
deliver the beams directly from the truck to
their appropriate sides of the
site. This operation involved a six-man crew. Two
men connected the hooks
from the crane onto the steel. Two men guided the steel
onto the planks on
the ground. Two men took turns operating the crane. This
process was very
time consuming due to the amount of steel needed to be lifted
entirely over
the five story structure to the other side of the site, and due to
what
seemed to be a lack of experience of the rigging crew. It took them a
very
long time to make the connections on each beam, and check for security.
These
factors may have influenced the unloading time taken that morning. As
these
trucks were being unloaded, another crew of men worked in the basement.
No
equipment was being placed at that time, but people were hauling down
tools and
what looked to be some sort of electrical cords. Perhaps they were
working to
install some piece of equipment already lowered down there, or
maybe they were
moving already dropped equipment away from the opening in the
floor to make room
for more to be lowered. January 28, 2000 Installation of
metal decking floor
supports began on Friday, January 28. By the early
afternoon, the level between
the first and second stories was nearly
complete. There were some openings left,
mostly on the south side of the
building, which will serve as stairways and
elevator shafts. The center of
the building also lacked decking, and judging by
the design drawings, this
section was left opened for a skylight, which will
cover the apex of the roof
upon completion. The decking between the second and
third stories was about
half installed by 3:00pm. A two-man team of welders
worked to secure the
union of the decking to the steel framework as each section
was placed.
Special protective masks and eye shields were used to ensure no
damage was
done to the eyesight of the welders during this process. Decking
sheets lay
in bundles on the beams between the third and fourth floors,
awaiting
installation. Upon completion, safety inspectors will come out to
the site to
check the torque on the bolts and the security of the welds. The
sheets were
placed connecting to studs sticking upward from the steel
framework. The outside
beams were such that they remained higher vertically
than the steel
reinforcement going in. This design allows for concrete to be
poured over the
decking without it spilling over the sides of the building.
This entire process,
including the welders, men placing the decking, and one
man who was sweeping
debris from the recently installed supports, entailed a
crew of seven men. Due
to the afternoon increase in snowfall, and the
increase of wind, the crew began
covering their equipment with plastic tarps
and prepared to quit for the day at
around 3:30pm. January 31, 2000 No work
was done on this site during the
weekend, but activity began again early
Monday morning, January 31. The 200 ft.
crane lifted three of six large steel
beams onto the top mid section of the
building, which will eventually support
a roof that slants upward from the fifth
story to the top of the skylight.
The crane was attached to the top of the beams
and lowered them vertically
onto the structure. Each beam had three small steel
ledges, which stuck out
horizontally near the top, and were designed to support
piping that will run
above the ceiling. Two men waited, standing on the fifth
story framework to
secure the beams in place once the crane had placed them.
These men drove
spikes into holes in the beam to anchor them to the structure.
Both wore
safety harnesses to ensure that they wouldn't lose their balance
while
hammering the beams in place. By noon, three beams were set and
secured. At the
same time the mid section steel erection was taking place,
another crew worked
to pump concrete into the basement of the structure. A
concrete mixing truck was
backed up to a pump truck, which had a long arm
reaching over into a hole in the
concrete foundation. Two men watched to
ensure that the materials flowed
smoothly from the mix truck to the pump
truck. Two other men stood near the end
of the long arm of the pump truck,
making sure the concrete reached its final
destination. Perhaps this meant
that all the necessary equipment for that area
of the basement was installed,
so the flooring was ready to be set. February 1,
2000 The afternoon of
February 1 was exceptionally slow. The blowing snow forced
the ironworkers to
abandon their placement of any additional decking. Storage of
steel beams is
adjacent to the construction site organized by type and size. The
steel beams
are the main materials being used during this phase of the
construction and
are closest to the workers for convenience and efficiency. A
few men worked
down below in the basement, but no surface activity was
happening. This delay
no doubt forced the schedule back for the completed
installation of flooring
reinforcement, and in effect caused delays for pouring
the floors. This leads
to a domino effect, pushing back the completion dates of
every other part of
the process dependent on the flooring being secured and the
basement
equipment being installed, which in essence, is every other part of
the
project. February 2, 2000 While observing construction on Wednesday there
were
approximately eight workers operating the machinery and working with the
steel
materials. Two men were on the ground going through the piles and
hooking up
pieces of steel to the crane. The crane operator would move the
beams away from
the steel beam piles to other workers who would bolt the
beams into position.
You could observe today that workers have begun to
lay steel sheets on the
second story that has already been assembled. This
steel is placed over the
floor trusses and then bolted down. Within in the
site there was a concrete
bucket for the crane, which will most likely be
used to pour concrete for the
individual floors. They can only lay the steel
and pour one floor at a time or
the steel from the above floor will be in the
way of getting the concrete bucket
through. Within the construction site were
piles of wire mesh and reinforcement
bars. This probably will be used as
reinforcement for the concrete floors.
Safety remained important through
out this phase of construction and was
demonstrated through rails, which were
placed around the floors and during the
systematic processes used during the
hooking and moving of individual steam
beams. There were four electricity
trucks present today and they appeared to be
digging the power supply line to
the building. Three men and a digging machine
conducted the digging of the
power supply line. February 3, 2000 On the
afternoon of Thursday February 3,
the site, just by looking, didn't seem to have
made any progress from the
previous day. However, workers were going down into
the basement. Due to
safety concerns, visitors were not allowed down below the
structure. In order
to find out what was happening, discussions with engineer
Charles Pickar
of Sebesta Blomberg and Associates, Inc. were used to fill in the
blanks. He
explained that the electricians and pipe fitters were working in the
basement
running conduit and laying pipe. As soon as they were done, the
fire
suppression people could get down there to spray the piping. They were
working
to get the necessary wiring complete so more equipment could be
lowered and
hooked up as soon as weather allowed. As for now, the site was
supplied power
through a shed, which was tapped into a near by permanent
power supply. Some
parts of the basement were already filled in, but one main
hole was left opened
to get the transformers and air handling units down.
Also in the basement, men
were laying diamond supports on the steel footings
to prevent cracking in the
concrete foundation from the stress of the
columns. These processes all
continued underground through the afternoon.
February 4, 2000 The snow and wind
on the afternoon of Friday, February 4
again forced the ironworkers to abandon
lying any additional floor decking. A
crew of three men prepared to drop a
transformer into the basement. The crane
was extendible and looked to be at
about 100 ft. The riggers took their time
securing the connection, but due to
wind, never attempted to move the unit.
Mr. Pickar later explained that this
particular type of crane is not very
stable. If the load sways while being
transferred, there is a great
possibility that it will flip. Keeping in mind
operator safety, as well as
the safety of nearby crewmembers, risks are just too
great to attempt
transfer today. Tarps covered the transistors and the crane
lowered and
folded up. Mr. Pickar also mentioned that a late delivery of hangers
for the
basement earlier in the project was already pushing everything
behind
schedule. The weather problems further added to those delays. Looking
at the
architectural drawings covering several tables in the construction
office, it
was noted that there will eventually be a tunnel running
underground out the
north end of the library and into nearby buildings.
Several revisions had to be
made on these drawings, especially in regards to
the structure itself, to modify
the ideas of the designer with the
feasibility of engineering. Sebesta Blomberg,
which is primarily an
engineering company, did most of the modifications. There
were almost 1000
pages just of architectural design and several other books of
drawings, such
as electrical and mechanical work, which were equally as thick.
These all
seemed to be labeled in an efficient manner to assure that pages could
be
easily located. This is especially useful when phone calls come in
and
someone needs to know something like a dimension on a certain machine in
a
certain room. People with identical books can easily direct another over
the
phone to a specific page. Depending on the type of work it entails,
specific
areas within each book are easy to find just by reading the markings
on the
bottom corners of the pages. Safety Issues In reference to safety
issues other
than the specific situations mentioned before, it was noted that
anyone entering
the site was required to wear a hard hat as well as
construction boots. Every
worker wore thick gloves and some wore safety
eyeglasses. All crane operations
were taken slowly and all ironwork was
called off at the first signs of
slickness or dangerous winds. Anyone
operating machinery, such as the welders or
crane operators were trained and
certified prior to working. All visitors were
required to sign in and out to
alert those in charge as to who was on site in
case of an emergency. The
construction office bookcase was filled with safety
manuals, OSHA guides,
project management workbooks, structural welding guides
etc. All the drawings
contained clear markings referring to placement of safety
equipment, such as
fire alarm and hose reels. Safety inspection was accounted
for in the
scheduling process and any sort of risks taken very seriously by all
members
of the working and management crew. Construction Observation
Conclusions
In conclusion, this construction project reflects a complex
system of seemingly
unrelated activities, which in actuality are crucially
dependent on one another.
The timing of the start and finish of every
little detail is scheduled so that
it fits in the order necessary to complete
the project in the most efficient
way. Advanced planning, foresight, and
experience are used to ensure processes
are done in the right order. An
example of this is the basement project. The
design must call for a section
of flooring to be left out. Hangers have to go in
before wire and pipes,
which have to go in before machinery, which has to go in
before fire safety
equipment and inspection, which has to be done before the
floor gets closed
up. Each link in the chain is essential. Delays can easily
build up fast if
one link can't finish the job. It's the responsibility of the
construction
manager to ensure that materials get there on time and that workers
have the
qualifications and tools necessary to complete the task. The
construction
manager must keep an eye on all aspects of the project, paying
special
attention to safety codes and restrictions, and understand
the
interdependence of each days events in order to avoid delays, maintain a
safe
working environment, and keep the schedule moving smoothly until every
final
detail has reached
completion.